Project Details
- Client
- Al Chaimaa Holding Limited
- Employer
- Datum Engineering Consultant
- Main Contractor
- High Star Contracting Co
- Value of Contract
- AED 12,970,000
- Status
- Completed
- Category
- Full MEP
Design, engineering, supply, installation, testing & commissioning, handover and maintenance of complete MEP works for residential buildings (G+4 Parking + 14 Typical + 1 Technical Floor + Roof) as per UAE regulations, complete.
- HVAC works
- Power works, transformer to power MDB
- Lighting and power works, MDB to power sockets
- Supply and installation of distribution circuit breaker boards
- Laying and installation of different types of cables
- Sanitary & drainage system
- Water supply system
- ELV systems
- Fire fighting & fire alarm system
More Projects
Abu Dhabi Future School — Phase 5, Pac 1
Client: ADEK View Project Details
Abu Dhabi Future School — Phase 5, Pac 1
- Client
- ADEK
- Employer
- Musanada
- Main Contractor
- Al Mansouri 3B
- Our Role
- MEP Contractor
- Status
- Completed 2018
Design, engineering, supply, installation, testing and commissioning, handover and maintenance of MEP works.
- HVAC works
- Electrical works
- Plumbing works
- Fire fighting system
- Fire alarm system
- UPS & central battery
- Structured cabling
- CCTV system
- Access control system
- Disabled toilet alarm
- AV systems
Mafraq Workers Camp — 44 Buildings
Client: Zonecorp View Project Details
Mafraq Workers Camp — 44 Buildings
- Client
- Zonecorp
- Main Contractor
- Al Jaber
- Our Role
- MEP Subcontractor
- Status
- Completed 2014
Design, engineering, supply, installation, testing and commissioning, handover and maintenance of complete MEP works for 44 buildings (G+2) as per UAE regulations.
- HVAC works
- Power works, transformer to MDB
- Lighting & power, MDB to sockets
- Distribution circuit breaker boards
- Laying & installation of cables
- Sanitary & drainage system
- Water supply system
- ELV systems
Al Forsan International Sports Resort
Client: Private Property Management View Project Details
Al Forsan International Sports Resort
- Client
- Private Property Management
- PMC
- IMCC
- Main Contractor
- Fibrex
- Our Role
- ELV Contractor
- Category
- Electrical
- Status
- Completed 2016
Design, engineering, supply, installation, testing and commissioning, handover and maintenance of electrical and ELV systems at Khalifa City.
- Supply & install transformer
- Supply & install QRM
- Complete LV substation
- Lighting control system
- Network infrastructure, passive & active
- CCTV, access control, bollards & barriers
- Hybrid PABX, intercom & wireless radio
- Public address system
- Master clock, almost 150 digital clocks
- IPTV system
- Audio visual system
- Traffic control system
- Race control system
Have a package to price? Send us the drawings.