Project Details
- Client
- Zonecorp
- Main Contractor
- Al Jaber
- Our Role
- MEP Subcontractor
- Status
- Completed 2014
Design, engineering, supply, installation, testing and commissioning, handover and maintenance of complete MEP works for 44 buildings (G+2) as per UAE regulations.
- HVAC works
- Power works, transformer to MDB
- Lighting & power, MDB to sockets
- Distribution circuit breaker boards
- Laying & installation of cables
- Sanitary & drainage system
- Water supply system
- ELV systems
More Projects
Al Barrari 3 Luxurious Villas
Client: Kamal Shihada View Project Details
Al Barrari 3 Luxurious Villas
- Client
- Kamal Shihada
- Employer
- Atrium Engineering Consultant
- Main Contractor
- Future Contracting Co
- Value of Contract
- AED 4,500,000
- Status
- Completed
- Category
- Full MEP
Design, engineering, supply, installation, testing & commissioning, handover and maintenance of complete MEP works for residential buildings (G+2 + Roof) as per UAE regulations, complete.
- HVAC works
- Power works, transformer to power MDB
- Lighting and power works, MDB to power sockets
- Supply and installation of distribution circuit breaker boards
- Laying and installation of different types of cables
- Sanitary & drainage system
- Water supply system
- ELV systems
- Fire fighting & fire alarm system
Essa Salem Residential Building
Client: Essa Salem View Project DetailsEssa Salem Residential Building
- Client
- Essa Salem
- Employer
- Safees Engineering Consultant
- Main Contractor
- Future Contracting Co
- Value of Contract
- AED 6,200,000
- Status
- Completed
- Category
- Full MEP
Design, engineering, supply, installation, testing & commissioning, handover and maintenance of complete MEP works for residential buildings (G+4 Typical + Roof) as per UAE regulations, complete.
- HVAC works
- Power works, transformer to power MDB
- Lighting and power works, MDB to power sockets
- Supply and installation of distribution circuit breaker boards
- Laying and installation of different types of cables
- Sanitary & drainage system
- Water supply system
- ELV systems
- Fire fighting & fire alarm system
ENEC Guest House & Visitor Centre
Client: Emirates Nuclear Energy Corporation View Project Details
ENEC Guest House & Visitor Centre
- Client
- Emirates Nuclear Energy Corporation
- Consultant
- Tangram Engineering Consultants
- Main Contractor
- Al Jaber Buildings LLC
- Our Role
- Subcontractor
- Category
- Electrical
- Status
- Completed 2016
Design, engineering, supply, installation and commissioning, handover and maintenance of the following electromechanical systems, complete.
- Lighting & power complete
- RMU & transformer
- Light control system
- Earthing & lightning protection
- Fire fighting, hydrant, hose reel & sprinkler
- Fire alarm system
- Fire suppression system
- UPS system
- Central battery system
- Diesel generator
- Data & voice infrastructure incl. WiFi
- CCTV & access control
- Audio visual & video conferencing
- Public address & voice evacuation
- IPTV system
- IP telephony system
- Building management system